Container Base Image Plan 3
Scope: DNS cutover and decommission of the old Alpine build. Only begins after Erik has approved the new Debian-slim deployment (Plan 2 Task 4 gate). Prior plan: Container Base Image Plan 2
Task 1 — DNS cutover
Once Erik has approved the new build (Plan 2 Task 4 gate passed), flip DNS to point to the new Debian-slim build.
- Update the DNS record for
librechat.uvilo.aito point to the new Debian-slim build’s Railway service - Verify
librechat.uvilo.airesolves to the new build and works correctly - Wait for DNS propagation (or as needed)
Task 2 — Verify and stabilize
Confirm the new build is stable at the production URL before tearing down the old one.
- Verify all MCP servers still work at the production URL
- Verify chat, git operations, and Forge scripts work at the production URL
- Monitor for 24 hours (or as Erik deems sufficient) for any issues
Task 3 — Moved to Plan 4
Decommission of the old Alpine build has been moved to Plan 4, which is deferred (no timeline set).